The committee steering the long-running Rethink Folly Road effort on James Island is lining up a second phase while the first heads toward construction.

Charleston County awarded the first-phase construction contract on Aug. 27, according to draft minutes of the Rethink Folly Road Steering Committee’s Sept. 9 meeting. The county put the project’s total cost at $6.3 million.

Phase one fills in missing sidewalk on Folly Road between Ellis Creek and Wilton Street, adds CARTA bus pads, shelters and bike racks at four stops, and mills and restripes the bike lanes with green markings at intersections, the minutes say. The project has a 450-day schedule and is set to finish by the end of 2027.

Getting there took three rounds of bidding. The county drew no bids the first time, and second-round bids came in over the available money, so it found more funding and bid the work again, according to the minutes. Committee chair Leslie Skardon, a Charleston City Council member, said “it’s finally starting” in a Nov. 18 Live 5 News report. Construction will begin in the new year, the station reported.

In September, the committee voted unanimously to make Folly Road between Bur Clare Drive and Battery Island Drive the focus of phase two and to seek design money for it, the minutes say. The minutes call it the most viable option, citing its lack of overlap with other projects and its expected cost.

The committee’s Nov. 18 agenda listed updates on a federal PROTECT grant application and a county transportation sales tax application for phase two design. Phase two will be built in segments, and some of the money will come from Charleston County’s transportation sales tax program, Live 5 News reported. Voters approved a new round of that tax Nov. 3, ABC News 4 reported.

The county won’t borrow against the new tax, so money for projects such as phase two must build up as revenue comes in, according to the September minutes. No cost or construction date for phase two has been released.

The overall project shrank this year. The Town of James Island opted out in May of an agreement tied to a state road safety assessment after residents and businesses objected to proposed raised medians, and several planned improvements were removed, Live 5 News reported in July.

The committee next meets Jan. 11.