A riverfront tract in Summerville that was once supposed to hold new homes is opening as a public park.
The Town of Summerville scheduled a grand opening for its 43-acre Ashley River Preserve on the morning of Nov. 20, according to the town’s events calendar. The preserve took six years to build, Live 5 News reported. Admission is free.
The land was initially supposed to be the site of new homes, Live 5 reported. That plan fell through, and the town bought the property. Neither the station nor the town’s project page gave a purchase price.
The town’s project page puts the tract at 43.65 acres next to the 7.61-acre Herbert H. Jessen Boat Landing off Ladson Road.
“Our goal was really to provide public access to the river and the property without changing the natural character of it so that everybody could really enjoy the beauty that’s here,” Amy Evans, the town’s parks and recreation director, said in Live 5’s report. The station described the preserve as a passive park for fishing and walking.
Funding came from Oakbrook tax increment financing, Dorchester County and the state’s Recreational Trails Program, according to Live 5. A tax increment financing district uses the growth in assessed value and property taxes inside its boundaries to pay for public improvements there, according to Dorchester County.
The county issued $15 million in limited obligation bonds on June 4, 2020, for four initial projects in the Oakbrook district, its website says. One was a $2 million contribution to the town for the preserve. In July 2022, the S.C. Department of Parks, Recreation and Tourism awarded the town a $100,000 Recreational Trails Program grant toward a $563,717 project it listed as the Summerville Preserve.
A master plan presented in November 2020 estimated the full build-out at $6,146,405 across seven sections, with about 152 parking spaces, four fishing piers and an amphitheater, according to the plan posted by the town. In 2021, the town approved an $868,673 first-phase contract with IPW Construction Group for dock repairs, a larger parking lot and a public restroom, Live 5 reported at the time. The town sought bids for a second phase in late 2025, according to a state procurement notice.
Neither the town’s project page nor Live 5’s report said how much of that plan has been built or what the work has cost in total.